Each development shall be
under construction within twelve (12) months after the date of approval of the
PUD final development plan, except as noted in this Section.
A. The
Township Board may grant one (1) extension of up to an additional twelve (12)
month period if the applicant applies for such extension prior to the date of
the expiration of the PUD or PUD phase and provided that:
1. The
applicant presents reasonable evidence that said development has encountered
unforeseen difficulties beyond the control of the applicant; and
2. The PUD
requirements and standards, including those of the Zoning Ordinance and Master
Plan that are reasonably related to said
development
have not
changed.