Sec. 22.13       TIME LIMIT FOR APPROVED PUD DISTRICT.

 

Each development shall be under construction within twelve (12) months after the date of approval of the PUD final development plan, except as noted in this Section.

            A.        The Township Board may grant one (1) extension of up to an additional twelve (12) month period if the applicant applies for such extension prior to the date of the expiration of the PUD or PUD phase and provided that:

            1.         The applicant presents reasonable evidence that said development has encountered unforeseen difficulties beyond the control of the applicant; and

            2.         The PUD requirements and standards, including those of the Zoning Ordinance and Master Plan that are reasonably related to said

development have not changed.