2007 MAY REPORT

DPW DEPARTMENT

 

 

 

  1. Bidding is out now for the 12th Ave. Sewer Project.  Bid opening is set for June 12, 2007.

 

  1. The 1 million gallon water tank was cleaned by our DPW Personnel.  Much credit to Mike and Joel for their hard work and the tank looks great.

 

  1. Dead end flushing has been completed for 2007.

 

  1. The Air Release Valve is now complete for 2007.

 

  1. The watermain replacement on Baldwin from Cottonwood to Rush Creek should start any time now.

 

  1. The Bluebird, Ridgewood, Chipwood, Chickadee and Broadview sewer projects are in the design stage as we speak.

 

  1. Three new construction projects for water and sewer are in our water and sewer department.

 

  1. We had 36 hydrant usages for pool maintenance for May 2007.

 

  • 19 new service connections
  • 6 new water meter installations
  • 76 final readings of water meters for home sales
  • 20 water service repairs
  • 65 new homes under construction

 

Respectfully Submitted

Denny Bishop