2007 FEBRUARY REPORT
DPW DEPARTMENT
- The
new 2007 DPW pickup truck has been delivered. It arrived two weeks early.
- 113
cross connections were accomplished with several corrections to be made
and numerous tests to be done.
- 5 new
grease traps inspected with 3 corrections to be made.
- Three
personnel attended the Joint Exp. In Lansing.
- The
following are a list of projects to be accomplished for the year of 2007.
- Hydrant
painting program
- Valve
exercise program
- Cul-de-sac
flushing program
- Bauer
elevated tank cleaning
- Inter
connect and dead-end flushing
- Two
lift station upgrades
- Two
fire hydrants were struck in auto accidents in February.
- There
was one service leak in February.
- Enclosed
is the annual report for 2006.
Ø
3 new sewer connections
Ø
10 new water meter installations
Ø
65 new homes under construction
Ø
6 water service repairs
Ø
23 final readings of water meters for home sales
Respectfully Submitted
Denny Bishop