2007 JANUARY REPORT

DPW DEPARTMENT

 

 

 

  1. The Cross Connection Program is being worked on diligently.  Thirty eight inspections were made during the month of January.

 

  1. A new pickup truck has been ordered and is scheduled for delivery on March 9, 2007.

 

  1. Repair of the GT1 Booster Pump is scheduled for February 2007.  This project must be completed by May 1, 2007, due to pump usage during the spring and summer months.

 

 

 

Respectfully Submitted

Denny Bishop