Minutes of the
work session of the Georgetown Township Planning Commission held Wednesday,
June 1, 2005
The meeting was
called to order by Chairman Honderd at 7:30 p.m.
Present: Huizinga, DeGood, Honderd, Pearson,
Poskey, Stasiak, South
Absent: none
The work session,
which formulated the agenda for June 15, 2005, included the following items to
be placed on the agenda, discussion, and action:
I.
Approval of minutes of the April 20, 2005 regular meeting and
the May 4, 2005 and June 1, 2005 work session meetings
III. Unfinished
Business
A. Preliminary
Plat of Cedar
Lake Estates No. 11
Revised plans were
submitted showing 11 additional lots for this phase and a letter was submitted
from the developer in regards to the construction of 28th Ave.
Todd Stuive, Exxel
Engineering, represented the applicant and presented the request. There are 30 lots proposed that meet or
exceed the LDR requirements in the ordinance.
The planner presented
a review and noted that the size of this phase has increased with the addition
of 11 lots.
When questioned
about the additional line on lot 173, the applicant stated that it was a
computer error. The applicant also
indicated that the owner of lot 176 would be required to maintain the portion
of the lot on the other side of the water.
The applicant stated that the goal was that the strip of land by lots
170 to 173 would be acquired by the lot owners and maintained by them, rather
than by the developer of Willow Creek.
He said that if an agreement could not be reached, the land would have
to be maintained by Boynton.
The zoning
administrator said that in the past when a temporary cul-de-sac had been put
in, the property owner of the lot that was impacted had difficulty installing
sidewalk because the location where it was to be located was asphalt. She asked that the developer be required to
install the sidewalks at the time the cul-de-sac was taken out and the new road
put in.
The applicant said that
he was aware of the situation and for this reason located the cul-de-sac after
the last lot in the phase so that none of the lots to be developed would be
affected.
Ed Stasiak asked
about the letter that was submitted by the applicant in regards to installing
28th Ave.
The zoning
administrator stated that the developer had submitted a letter stating that he
would be financially responsible to install that part of 28th Ave.
that was impacted by this development, but the developer still had to sign a contract
with the Township in this regard. She
asked that the Planning Commission make this a condition of approval.
Cornelius Huizinga
asked if the lots would have lake access if that strip of land was acquired for
lots 170 to 173.
Greg Honderd asked
how that strip ended up being created.
The applicant said
that it was a lack of coordination between the developers, plus the requirement
that excavating take place away from the property line.
The planner
suggested that the request be left tabled until the following issues could be
resolved: the contract signed by the developer, an approval letter submitted by
the Road Commission, the applicant can look into obtaining the strip of land
abutting lots 170 to 173, and the site plan could be cleaned up with the site
plan issues such as the acreage shown and the computer error be eliminated from
lot 176.
B.
Site Plan (ST0508) Campus
View Townhouses-10081 42nd
Ave.
The item is going before the ZBA on May 25, 2005 and the applicant is seeking a variance to not have attached garages. The item was left tabled.
IV. New
Business
A.
Site Plans
#050601-01 – Site Plan (ST0509)
The Township is installing a new lift station at 4425 New Holland
St. Although the Township is immune from
the Zoning Ordinance, the DPW Director asked that the plan be reviewed. It will be located in an AG district and the
setback requirements are met. No
sidewalks are required in the AG district.
Landscaping will be provided by the building.
Moved by South, seconded by Poskey, to accept the site plan as
presented for information for the Township metering station.
MOTION CARRIED.
2. (ST0510) Randy Rottschafer-610 Baldwin
Randy Rottschafer
presented the request and stated that he had built the strip mall and was
requesting to add an accessory building.
The planner stated
that the proposed accessory building meets setback requirements; however,
square footage and height must be provided along with verification that the
architecture of the proposed structure is consistent with the main structure.
The zoning
administrator asked the Planning Commission if they would provide a condition
of approval that if the decel lane is not added, the driveway that goes into
the front yard would be removed. The
Planning Commissioners decided not to add such a condition because they said
that the decel lane would have to be added as some point in the future and did
not want the applicant to have to remove the drive and landscape if it would be
torn up in the future.
Greg Honderd said
that he would like to see on paper that the accessory building would be
architecturally similar to the main structure.
Michael Pearson
asked for a time line for the decel lane.
The zoning
administrator said that there was no time line and money was the issue.
Del South said that
it would have to be completed at some point.
The applicant asked
if a letter in writing would suffice for the assurances that the accessory
building would be architecturally similar.
The zoning administrator
said that they had accepted a written statement in the past from applicants for
assurances that an accessory building would be architecturally similar.
B. Public Hearings
1.
Special Use Permits
a. (SUP0504) Wizard Wash Ventures, LLC, 4346 Leonard NW, Grand Rapids, is requesting to have a vehicle wash establishment under Sec. 15.3(C), on a parcel of land described as P.P. # 70-14-13-300-075, located at 550 Baldwin St., in a (CS) Community Service Commercial district
Bill Bussey, part
owner, represented the applicant and presented the request. He said that he had been involved in the
Cottonwood Center and said that he wanted to use the under-developed property
for a car wash. He said that the
proposed car wash was slower than the tunnel and would take about six minutes
for each wash. He said that there was
adequate room for the traffic that was anticipated and it would not interfere
with the convenience store. He said that
the setback would be 110 feet from the centerline of Cottonwood and the exit
was 24 feet from the property line. He
said that although no landscaped legend was provided, he planned to mimic the
same landscaping as Cottonwood Center.
He said that he would provide a landscape legend and have bushes. He said that sidewalks would be provided
along the Meijer property and that the dumpster would be relocated.
The planner
presented a review and said that site plan requirements were not obviously
shown on the site plan. He said that
setbacks should be shown from the vacuums.
Signage should be shown as only a wall sign. Floodplain information and a location sketch
should be shown. Sidewalks should
connect to the sidewalks along Cottonwood Center. The legal description for the leased property
was adequate. Water disposal information
should be shown since the Township must adhere to the State requirement for
illicit discharges.
The applicant
explained that there were strict requirements for disposing of the water,
including separating the oil and having it picked up by a hauler to be disposed
at a dump.
The planner said
that building elevations should be provided to show that it is harmonious with
the other structures. He asked if a
letter of approval was given for the water disposal.
The applicant said
that a plumber would install the disposal system and a note could be added to
the plan.
The planner said
that screening details and a landscaped legend should be provided. He said that there could be a conflict with
circulation and the landscaping along Cottonwood should look more attractive.
The applicant said
that the dumpster would be picked up during slow times when other people would
not be there.
The planner said
that the sidewalks have to be connected because there should not be a break in
the sidewalk on the other side of the entrance.
He said that he understood the issues; however, the sidewalk would have
to be continuous to be effective even if coordinated efforts were difficult.
The applicant said
that he had spoken with Greg from Meijer and he anticipated an answer by next
week.
The planner said
that the area should be safe for pedestrian and vehicular circulation. He said that the overall circulation pattern
should be part of the next submittal, showing queuing, stacking, flow in and
out, and pedestrian circulation and showing the relationship between other
buildings in the development. He said
that it should be demonstrated that the vacuums are at least 90 feet from the
centerline of Cottonwood. Dimensions
should be shown.
The zoning
administrator said that the applicant had done a great job on Cottonwood Center
and he just needed to show what he was going to do here.
The applicant said
that the landscaping would be the same as Cottonwood Center.
Greg Honderd said
that the car wash works well with the gas station and that an escape lane should
be provided for those who choose to exit before getting to the car wash
building. He said that the location of
the vacuums would be cumbersome because cars would have a difficult time
getting back out with traffic. He said
that this is a busy congested area and the vacuum location does not work
well. He said that it would be difficult
for a vehicle exiting to make a left turn, particularly during busy times such
as Saturday mornings and that the vehicles could be stacked into the
intersection. He said that the applicant
should consider moving the car wash to the other side.
Michael Pearson
asked about accessing the dumpster on the northwest corner.
The applicant
indicated that he would explore the option.
Michael Pearson asked
to clarify landscaping and the applicant indicated that that the landscaping
would be inside the sidewalk on the Meijer property and not along the
street. He said that although he
understands that they can’t control what they don’t own, they should continue
to improve the area by buffering the asphalt.
The applicant said
that Meijer is protective of their property and it takes a long time to get
them to agree to changes on their property.
He said that he planned to pick dwarf trees and specify the plantings
that would be added.
Del South said that
he was concerned with traffic and that lines would form due to the six minute
wash. He said that there was no room to
get out.
The applicant said
that they had looked at a lot of different versions but wanted to stay away
from the convenience store traffic. He
said that signage could be provided for a right-turn only.
Ed Stasiak asked
about the other vacuums.
The applicant said
that the customers could park on either side and hoped the Meijer
vacuums would be eventually eliminated.
The planner
suggested that an internal traffic analysis be performed during peak hours
because of the concern with traffic and he said that signage could restrict
traffic circulation during peak hours.
The applicant said that
their customer numbers depend on the weather and were normally busiest on
Friday, Saturday and Sunday. He said
that they were slow in the summer but made their money in the winter months.
The Planning
Commission directed that the applicant not be advertised for a public hearing
until some of these issues could be addressed and a revised plan be submitted.
2.
Rezonings
a. (REZ0502) To change from (I) Industrial to (LDR) Low Density
Residential a parcel of land described as P.P.# 70-14-31-200-067, located at 5565 40th Ave.
The Board initiated
the rezoning from I to LDR with motion #050411-11. A house and residential use has been located
on the site for about 40 years and LDR is consistent with the Master Plan.
The planner said that it is an opportunity to remedy a non-conforming situation. He said that he reviewed the request and it is compatible with the surrounding area, consistent with the Master Plan and capable of the uses in the LDR district.
5.
Plats
a. Preliminary Plat of Georgetown
Shores No. 6
Todd Stuive, Exxel
Engineering, represented the applicant and presented the request. He said that this is the last phase and will
eliminate the gravel mining. He said
that there are 48 lots, most with lake frontage, and all comply with the LDR
requirements. He said that there would
be a tunnel for boats to access the bigger lake. The plat will be served by sanitary sewer and
have public water. The road was proposed
to line up with Springmont. Sidewalks
would be installed by the developer along Edson and connect to 18th
Ave., and would be installed on individual lots according to ordinance. He said that the homeowners desired to
eliminate the connection to 18th Ave. because it would create a
confusing “T” 3-way intersection that would empty into secondary or residential
streets and because the residents did not want traffic other than local
resident to use or cut through the street.
They did not want anyone other than those with a vested interest to use
the road. He said that people would not
pay attention to speed limits. He said
that they Road Commission did approve the layout as submitted.
The planner said
that the bike path along VanBuren and 14th Ave. must be redone and
the Road Commission wants a new letter of Credit. He said that the Township Board could require
that the drive connect to 18th Ave., though he did understand the
residents’ concerns. He said that the
plan should indicate sidewalks, specifically for lots 320 and 319.
The applicant said
that note 7 says that sidewalks would be constructed as individual home sites
are constructed and the developer will put the sidewalks on the double frontage
lots as required.
The planner said
that the connection to 18th Ave. would require the redesign of the
lots and landscape preservation should be noted. He said that the bike path had to be redone.
The applicant said
that patching had been done to the bike path and they were preparing to redo
the whole path by June 22.
Ron DeGood said that
18th Ave. would be a busy intersection and he did not know if people
would cut through. He said that rather
than sending the traffic through the new plat, he would like to see them exit
onto 18th Ave. He said that
with the current layout, they were putting a lot of traffic through the new
plat.
The applicant said
that it would be for the convenience of some and the inconvenience of the
rest. He said that they would have a
choice to buy in the new plat or not.
Mike Prelewitz,
Ottawa Aggregates, said that they would be done digging this season and they
would be tearing down by next spring. He
said that traffic was not coming to the development and would be deterred all
the way and would have to slow down. He
said that they currently keep the gate shut as required and people drove
through the lots. He said that it was a
bad intersection and the lake association wanted to slow the traffic down. He said that this layout benefits those in
the association.
Ed Stasiak said that
if the road is connected to 18th Ave., there would be additional
traffic and they should discourage the traffic any way they can.
Greg Honderd said
that when he first saw the layout, he was not so sure and that they would have
to stop first. He said that if they
don’t connect, the traffic would either go to 16th Ave. or to 14th
Ave. or go around.
The applicant said
that the plat was submitted to the Road Commission and he has the letter of
approval where they asked for the new letter of credit.
The planner said
that traffic calming techniques could be used.
Del South said that the
current layout would increase traffic and there would be more accidents and
more traffic going around rather than to 18th Ave.
Ron DeGood was
concerned that traffic would cut through Green Meadows.
Greg Honderd said that
it would be best to connect with 18th Ave. and have a stop sign
rather than have traffic going around the 5 acre lake.
6.
PUD’s-none
a. Chapter 24 footnote (b)
ii
b. Sec. 3.7
c. Chapter 24 footnote (o)
d. Sec. 22.5 (A)(1)(z)
e. Sec. 22.8(D)(4)(i)
f. Sec. 3.4
The Board initiated
the ordinance amendment to Chapter 24, footnote (b)ii to include Balsam Dr. in
the list of streets requiring that the setback be measured from a point 60 feet
from the centerline of the street with motion #050411-10. The list currently includes 28th
Ave. and it was an oversight to not include Balsam because at the time it
probably wasn’t noticed that the street has a name change for three parcels
before the City of Hudsonville line.
An amendment is
proposed to permit a maximum of a five foot wide handicapped ramp to project
into a required front yard setback. The
planner has indicated that the PC might want to “tweak” the language to include
required side and rear yards.
An amendment is
proposed to require floodplain information for PUDs. The State has begun strictly enforcing
floodplain management and this would help with determinations as to whether a
site is located in a floodplain.
An amendment is
proposed to clarify how big an eave could be on an accessory building.
The proposed
amendments are as follows:
Chapter 24, footnote
(b) ii
Balsam Dr.
Sec. 3.7 BASIS OF DETERMINING FRONT YARD REQUIREMENTS.
The
required front yard shall be measured from the right-of-way line to an
imaginary line across the width of the lot which represents the minimum
required front setback distance for that district provided that where an
average setback line less than required has been established by existing
buildings on the same side of the street and within two hundred (200) feet of
the proposed building, such established setback shall apply. However, no reduction in the minimum required
front yard setback shall be permitted along those streets identified in Chapter
XXIV, footnote (b). Unenclosed porches, steps or similar
facilities may project into a required front or rear yard for a distance not to
exceed twelve (12) feet. In the case of a handicap wheelchair
ramp (not to exceed a width of five (5) feet), the Zoning Administrator may
waive ANY setback requirements at his/her discretion, if no other options are
available to provide a ramp, provided that the applicant agrees to remove the
ramp if it is no longer necessary on the property. A performance letter or performance guarantee
may be required.
(o) Projections Into Yards. Architectural
features, as defined, not including vertical projections, may extend or project
into a required side yard not more than two (2) inches for each one (1) foot of
width of such side yard and may extend or project into a required front yard or
rear yard not more than three (3) feet. An open porch, paved patio, deck or
terrace may project into a required front or rear yard for a distance not to
exceed twelve (12) feet. (revised 1-24-05). In the case of a handicap wheelchair ramp (not to exceed a width of
five (5) feet), the Zoning Administrator may waive ANY setback requirements at
his/her discretion, if no other options are available to provide a ramp,
provided that the applicant agrees to remove the ramp if it is no longer
necessary on the property. A performance
letter or performance guarantee may be required.
A.
Preliminary
Plan Application Requirements
1.
A completed application form and ten (10) copies
of a preliminary development plan shall be provided to the Zoning
Administrator. The preliminary plan
shall contain the following site plan information:
z. Floodplain
areas.
D. Final
Development Plan Application Requirements:
4. A
site plan containing all of the information required in this PUD Chapter and
the
following
information shown below: (If the plan consists of phases, then the
above-mentioned information is only required for the specific phase(s) being
presented for final approval. Each
subsequent phase shall be reviewed in the same manner).
i. Floodplain
areas.
(C) No
detached accessory building or use shall be located closer than ten (10) feet
to any main building , nor shall the eave line (which could be a maximum of three (3) feet) of such
building be located closer than five (5) feet to any side or rear lot
line. All accessory buildings shall meet
the same setback requirements from a street right-of-way line as required for
the main building, provided that on a double frontage lot, an accessory
building may be located within the required rear yard no closer than twenty
(20) feet to the road right-of-way line.
V.
Other Business
VI. Commissioner Comments
VII. Staff Comments
VIII.
Adjourn
The meeting was
adjourned at 9:30 p.m.